The decision has been made because Watt Power (the parent company of Abergelli Power) was unable to secure contracts for its two consented 299MW gas-fired generation projects (in Suffolk and at Hirwaun, near Aberdare) through the Government’s recent Capacity Market Auction for future power generation (held in December 2015). If contracts are secured for these two consented projects in the Government’s next Capacity Market Auction (to be held in December 2016), Abergelli Power would look to submit a Development Consent Order application in 2017.
The City and County of Swansea, the local planning authority, has been notified.